BC_fieldvisit_15







The only site that was not slowing down due to the weather was the West AJ renovation.  Walking by it the day before there was some work being done to the exterior, mainly removal of hokie stone, but today all of the subs that were on site were dealing with interior systems such as HVAC, and carpeting.  This is the biggest advantage to this job site compared to the others.  If the weather is awful work is still going to be done.  This would make the schedule for the West AJ renovation a lot more flexible.  It also appeared as I walked by the site that the scaffolding was off limits in such heavy rains.  A week ago the scaffolding was being utilized a lot but I didn't see one person on it when I visited the site.